Process Cost Calculation Formula ( Manufacturing Cost Calculation / Production Cost Calculation Phase 2 + 3 )
For Calculating Process cost, we have taken an example of drilling operation,
Firstly, we should have knowledge about the number of processes to be
performed to make a particular product,
We should have knowledge about the total cost imposed on each and every operation. We should have knowledge about the labor wages,
We should have
knowledge about the land rent, electricity charges, machine power, etc.
We should have
knowledge about the yearly production
For example
Let’s
say that there are two processes namely
1.
Drilling
2.
Gauging
Here we
are discussing only the drilling process to understand the concept of process cost
Now, we will try to find out
the process cost of the drilling process
Process cost is the main phase
of finding out the cost of a product, so understand it carefully.
Calculation of Process cost
For finding out the Cost
imposed/drill done, various factors have to be studied: -
Let us
assume the following information
Drilling Machine Cost = Rs
50000
The lifespan of Machine = 5 years
Drill
bit used per year = 100 nos
Cost of
Drillbit = Rs 5 / Piece
Labour
working on machine = 1, Helper =1
Wages
per month per Labour = Rs 2500
Electricity
Charge = Rs 6/unit and in 1 day 10 units were consumed
Land
rent of area, where the machine is installed = Rs 100/Month
Let us assume that there is an order of 60000 pipes with a single drilled hole in it for a whole year. So first we will find out the number of working days in a year
= 365 – 52 Sunday – 13 festival
days = 300 working days
Now
first we will find every cost per piece step by step then we can easily find
the cost imposed per drill done.
Calculation of Labor cost
As
there are 60000 pieces to be delivered in 300 working days so
Per day Production = 60000/300
= 200 pieces
Let us
suppose that factory is working in one shift of 8 hours
So Per hour production = 200/8
= 25/hour
So the production = 25
pieces/hour,
Labour working = 2 nos
Labour wage given = 2 X 2500 =
Rs 5000/month
Labour wage per day = 5000/ 25
days (Working days in a month)
Labour working = 2 nos
Labour wage given = 2 X 2500 =
Rs 5000/month
Labour
wage per day = 5000/ 25 days (Working days in a month)
Calculation of Consumable
tooling cost
Production = 25 pieces/hour,
Drill bit
used = 100 no's/Year
Drill bit
cost = Rs 5/Bit
Drill bit
total cost = Rs 5 X 100 = Rs 500
Drill bit
cost per day = 500/ 300 days (Working days in a year)
Drill bit
cost / day = 500/300 = Rs 1.66
Drill bit
cost per hour = 1.66/8 = RS 0.2075
So Drill bit Cost/Piece = Rs
0.2075/25 = Rs 0.0083
Calculation of Electricity
consumed
Production = 25 pieces/hour
No of machine working = 1 no’s
Per Unit rate =
Rs 6/Unit
No. of
unit consumed per day per machine = 10
Electricity cost per day = 6 X 10 = Rs 60
Electricity cost per hour = Rs 60/8 = RS 7.5
Electricity Cost/Piece = Rs 7.5/25 = Rs 0.30
Calculation of Land Rent Price
Production = 25 pieces/hour,
Land rent of space on which
machine is installed = Rs 100/month
Land rent of space = Rs 4/Day (25working
days in a month)
Land rent of space = Rs 4/8
Hours
Land rent of space = Rs 0.5/
Hours
Land rent of space/Piece = Rs 0.5/25 = RS 0.02
Calculation of Machine cost
Production = 25 pieces/hour,
Machine Cost = Rs 50000/ 5Year
Depreciation cost = Rs 50000/5
years = Rs 10000
Cost per piece = Rs 10000/
60000 (total production in a year)
So, Machine cost / piece = RS 0.17
Final Sheet for calculation
of Process Cost
Production
= 25 pieces/hour,
1. Labour Cost = Rs 1 /Piece
2. Consumable tooling cost = Rs
0.0083/Piece
3. Electricity Consumed = Rs
0.30/Piece
4. Land Rent Price = Rs
0.02/piece
5.
Machine Cost = Rs 0.17
So, the total process cost will be the sum of all the above costs
= Rs 1+0.0083+0.30+0.02+0.17 = Rs 1.4983
Step 3.
Final Phase of Manufacturing cost
For calculating
overhead and other cost, firstly we should know about all other
factors that affects the manufacturing cost of a particular product. We should
know about the total cost imposed on each and every operation
As we have already calculated the two cost
1. Raw
Material Cost
2. Process
Cost
Now we will do the calculation of overhead and other cost
imposed on the above two costs.
Factors
that effects the overhead and other cost are :
Rejection
Cost
Overhead
Cost
Inventory
Carrying Cost
Profit
Tool
Amortization Cost
Brought out
Product Cost
Rejection
Cost
Whenever we makes products in mass production, there is chance of
rejection also that the products which are produced are not 100 % accurate and
there is chance that some manufactured products may differ from the actual
products and if they are out of tolerance limit, they will be counted in
rejection.
In general,
we take rejection as 1 % imposed on the total (raw material + Process) cost.
Overhead
cost
It is the indirect expenses of operating a business that range from rent
to administrative costs to marketing costs. It may includes rent, staff
salaries, liabilities , insurance cost, utilities, accounting cost, telephone
bills, office supply, advertising and promotions etc.
In general, we take
overhead cost as 15 % imposed on the total process cost.
Inventory
Carrying cost
It is the total of all expenses related to storing unsold goods. We have to keep a separate space for storing inventory that is ready to dispatch material. We store this material to overcome any type of shortage to the customer so we keep inventory to us.
In general,
we take inventory carrying cost as 1 % imposed on the total raw material cost.
BOP
(Brought Out Parts) Cost
If we are using any type of Brought out part (BOP) to be assembled in our
product before providing to the customer then the amount of BOP assembled will
also be added in our costing sheet.
This amount
is directly added as received from vendor or market.
Final Sheet for calculation of Overhead and other Cost
So the
total cost will be sum of ( C to I ) = Rs 14.56
For more information.
Please see my video on youtube at the following link
For English language https://youtu.be/pLe4B92fh_A
For Hindi Language Part 1 https://youtu.be/dyw6deHOMNM
For Hindi Language Part 2 https://youtu.be/x_VN1NBZA1s
For Hindi Language Part 3 https://youtu.be/KsxsZLlE3Pw
Comments
Post a Comment